|
New project types
Over the last decade, new project financing models have appeared changing the way the construction
sector operates and forcing consultants to modify their traditional role so as to continue participating in
the overall project development process.
Traditionally, project financing is the responsibility of the Client. The Client normally hires Consultants to
plan and design his work, and then calls for tenders from Contractors. Consultants assist the Client in
evaluating the tenders, in preparing construction contracts and in supervising the execution of the work.
Under the traditional system, the role of the Consultant is clear since he works for and is paid by the
Client only.
Turnkey
In a variation of the traditional project development model, Clients sometimes make Contractors
responsible for design as well as construction. Sometimes Contractors with limited design experience
or capability then hire Consultants to develop the necessary designs. In this case, the Contractor becomes
the Consultants Client, and the Consultant works solely for the Contractor. The Consultant has no
financial interest in the Project other than his fee for the work he performs, and the financial investment is
made by the Owner.
FIDIC dealt with this alternative in a Policy Statement on the Role of the
Consulting Engineer in Turnkey Projects.
New project financing models
This Policy Paper deals with the Consultants role in projects where he will have a financial interest
other than his usual consultancy fee. It has been prompted by recent developments in project financing
where the participants, including the Consultant, must carry financial risks different than those normally
assumed under the traditional roles.
These new project financing models include:
- Build-operate-transfer (BOT) Projects, where a consortium builds a Project and then operates it for a
given period to recover part, or sometimes all, of its investment through revenue derived from operation
of the Project.
- Projects which Consultants develop at their own cost with the idea of selling them to Developers.
These two alternative project development systems are explained below.
BOT or BOOT schemes
Under build-operate-transfer (BOT) or build-own-operate-transfer (BOOT)
systems, consortia of Contractors, equipment suppliers, Consultants and financiers undertake to finance,
design, construct, and operate projects and, at an agreed time, transfer them to their ultimate Owners.
Some power plants, toll roads, tunnels, and bridges are now being carded out under BOT systems, and
the consortia recover the cost of their involvement through the collection of tolls, sale of electricity to utility
companies, etc.
In some BOT Projects, Consultants are paid for their services directly by the consortia as the services are
performed. The position of the consultant in this situation is similar to that of turnkey or design/construct
contracts. In other BOT Projects, the consortia partners will require that everybody participating in the
venture make an investment, which, in the Consultants case, will typically be his usual fee to be
recovered over the operation period of the Project, from the revenue it produces, together with any
premium for his risk which may have been agreed with the consortia partners.
In all projects where the Consultant does not work directly for the Owner, a risk of uncertainty exists. It is
important, therefore, that Consultants always make absolutely clear who their Clients are for any given
project. The Consultants Client may be the Owner, a Turnkey Contractor, or a Consortium of which
the Consultant is a member. Should the Consultant be asked for advice by parties other than his Client he
should recommend that they seek it elsewhere, i.e. by engaging their own experts as necessary.
Changes in design
A particular problem exists in cases where the Consultant has been involved in the initial planning for the
Owner, but at a certain time, at the suggestion of the Owner, is retained by either a Turnkey Contractor or
made part of a BOT consortium. In this case the Owner may expect that a Consultant will continue the work
according to the original plan, whereas the Contractor or the Consortium, for various reasons, may want
design changes. In such a case, the Consultant should make the Owner aware of this possibility, in writing,
at the time when his work for the Owner is terminated, and his work for the Contractor or the Consortium
is about to start.
If changes in the original design are required by the Contractor or by the Consortium, the Consultant should
carefully evaluate the effect of such changes and advise the Contractor or the Consortium accordingly. Should
the Consultant consider the proposed changes technically unacceptable, he must so advise the Contractor or
the Consortium, and refuse to implement the changes.
FIDIC believes that it is in the interest of the community at large that independent Consultants participate in
BOT projects, since they have considerable experience in technical matters. Accordingly, FIDIC has changed
it statutes to allow independent consultants to participate in BOT schemes, either as a consortium member
or as a consultant to a consortium.
The ultimate Owner, (public utilities, road or bridge authorities, etc.) should realise, however, that the Consultant
who is a member of a BOT Consortium is not its consultant, and should, therefore, carefully consider whether
it has sufficient in-house knowledge to evaluate the technical aspects of a Project. If the ultimate Owner does
not have such expertise, the Owner should engage its own consultant to act in the Owners interest.
No split responsibilities
FIDICs policy is that one Consultant should, simultaneously, not advise both the eventual Owner and
the BOT Consortium on the same Project. The eventual Owner may want to solicit technical advice from the
Consultant in a BOT Consortium, but the Owner and the Consultant must keep in mind that the Consultants
obligations are solely to the Consortium.
Projects promoted by Consultants
In cases where a Consultant promotes his own project, he should make sure that the concept is technically sound.
When he tries to sell his project to an Owner or a Developer, he must make his own financial interest in the
continuation of the project absolutely clear, in writing. The Consultant should also advise the Owner and/or the
Developer, if a second opinion on key items of technical and/or financial nature should be obtained from other
Consultants.
Pitfalls to guarded against
Whenever Consultants are involved in a project other than in the traditional role of Consultant to the Project Owner,
there is potential for conflicts of interest.
FIDICs policy
Independent Consultants are encouraged to participate in the promotion of design/construct, BOT and similar projects,
working either as consultants to the project implementing parties or as consultants to the Owner/Operators, ultimate
Owners of BOT projects and other interested parties.
- Consultants should not work for or represent more than one Client on one project unless all parties concerned
are fully aware, in advance, of the Consultants participation and accept such arrangement in writing.
- When participating in projects where a Consultant has a financial interest other than his normal fee, he must
advise all interested parties accordingly, in writing and in advance of performing services.
- When a Consultant has participated in a project as Consultant to the Owner and changes his role to advise
either a Contractor or to be a member of a Consortium, he must make the Owner aware, in writing and in advance,
of this role change, and the fact that the Owner will no longer be in a position to benefit from his advice.
- To avoid compromising the technical or functional suitability of a Project, Consultants, who elect to work for
Contractors or Developers, or to have a financial stake in a project, must:
- define clearly at the outset what the Consultant is to do and to what degree of detail designs and drawings
are required;
- establish that the Consultant will receive compensation adequate to cover his services, whether contingent
upon the project proceeding or not; and
- resist any effort to deviate from the Consultants pre-established definition of the work unless all parties
concerned in the Project are in full agreement, and the Consultant, himself, agrees that such deviation is the
correct course.
- Consultants should carefully investigate the liabilities they will assume with projects where they have a
financial interest and seek insurance against such liability (Insurers must be notified, in writing, by Consultants
who plan to be involved in such projects).
- Consultants who have developed their own projects should recommend to concerned parties to seek a second
opinion on key technical and/or financial items, if such parties are unable to evaluate the risks and benefits themselves.
Otherwise, the consultant will have a vested interest in having the project proceed. Any study needed to develop such
a second opinion should be carried out at the level of detail required.
Approved by FIDIC Executive Committee in September l994
|