| FIDIC |
Home Site
search Site map Contact FIDIC New News Directories Diary Products Account |
| BOOKSHOP | RESOURCES | CONFERENCE | INTERNAL | REGIONS | FEDERATION | |||||
| Welcome Contracts Agreements Practice Training Development Information | ||||||||||
| The New FIDIC Forms |
| Daniel Atkinson, 1999 |
|
Background The Federation International des Ingénieurs - Conseils (FIDIC) is the leading body for the development of model standard forms of contract for use in the international construction industry. The standard forms are generally accepted by Employers and Contractors as providing a balanced allocation of risks and providing fair procedures for administration of contracts. In September 1998 FIDIC published "test editions" of its forms of contract in a new livery of colours Red and Yellow to update the existing Red, Yellow and Orange Books. FIDIC also introduced a short form of contract in another primary colour - the Green Book. A metallic colour has now been added in the Silver Book which is likely to be the most controversial form The new Red Book is the traditional form for civil engineering construction in which the Contractor constructs to the Employer's design. There is however provision for the Contractor to carry out design where specified. The form maintains the role of the Engineer and the payment mechanism is based on measure and value. The new Red Book revises the previous Red Book version and incorporates current thinking on the management of contracts The new Yellow Book replaces the existing Yellow and Orange Books. It is intended to be used for Design and Build contracts and for Plant Contracts. The Engineer administers the contract and payment is on periods or installments of the Lump Sum The Green Book is an entirely new FIDIC form and adopts the overall risk philosophy of the Red and Yellow Books. It is intended for contracts of low capital value or simple contracts of short duration such as dredging works. There is no Engineer and the payment mechanism is required to be specified in the Appendix to the Form of Agreement, but payment is at monthly intervals The new Silver Book is an entirely new FIDIC form for BOT and similar projects. It is intended to be used on fixed-price turn key projects. There is no Engineer, instead the Employer deals directly with the Contractor. Risk is placed largely with the Contractor. Payment is on periods or installments of the Lump Sum One form of contract missing from the new livery is the Target Cost Reimbursable form of contract. This is not widely used internationally but is used extensively in the UK and particularly on tunnelling contracts. Available standard forms are the IChemE Green Book and the ECC Options D and E which have all been used with some success Allocation of Risk In many projects one of the significant risks is that of changed Site and Ground conditions. The starting point is the responsibility for supply of information Clauses 4.10 and 4.11 are the relevant provisions in the Red and Yellow Book. Clause 4.10 requires the Employer to have made available, 28 days prior to the latest date for submission of the Tender, all relevant data in his possession on sub-surface conditions at the Site. The Contractor is only responsible for interpreting the data. Under Clause 4.11(b) the Contractor is deemed to have based the Contract amount on such data, and in the case of the Yellow Book any further data relevant to the Contractor's design. This effectively means that the Employer warrants the accuracy of the information he has provided Under Clause 4.10 the contractor is also deemed to have obtained all necessary information as to risks which may influence or affect his Tender or the Works. He is deemed to have inspected and examined the Site and other available information. However, these "deeming" provisions are limited to the extent that the investigation by the Contractor is practicable, taking into account cost and time Clause 4.12 defines the allocation of risk forchanged ground which in the Red and Yellow Books follows the traditional forseeability test. The Employer carries the risk of physical condition which could not have reasonably been foreseen by an experienced contractor by the date for submission of the Tender. Physical Conditions is defined as both natural physical conditions as well as man-made and other physical obstructions and pollutants. The definition excludes climatic conditions, but includes hydrological conditions The Green Book (Short Form) is silent on the matter of supply of information. Clause 6.1 defines the Employer's risks which include changed ground . Sub-clause 6.1(b) includes as an Employer's risk any operation of the forces of nature affecting the Site and/or the Works which were either unforeseeable or against which an experienced contractor could not reasonably have been expected to take precautions. Sub-Clause 6.1(e) defines as the Employer's Risks physical conditions or obstructions other than climatic conditions where were not reasonably foreseeable by an experience contractor The Silver Book adopts a different approach. The Employer is required to have made available to the Contractor all relevant data in the Employer's possession on hydrological and sub-surface conditions at the Site. The Contractor however is responsible for verifying as well as interpreting the data. There is therefore no warranty by the Employer of the accuracy of the information The Silver Book allocates all the risk of changed ground conditions to the Contractor. Clause 4.11 provides that the Contractor is deemed to have satisfied himself as to the sufficiency of the Contract Price, and states that it covers all things necessary to design, execute and complete the Works. Clause 4.12 provides that the Contractor accepts responsibility for having foreseen all difficulties and costs of successfully completing the Works. Controversially the Silver Book at Clause 5.1 also passes to the Contractor responsibility for the accuracy and completeness of the Employer's Requirements. The Employer is expressly stated not to be responsible for any error, inaccuracy or omission in the Employer's Requirements. The Employer is only responsible for the definition of the intended purpose of the Works and the criteria for testing/performance of completed Works. The more usual provision for responsibility for the Employer's
Requirements is to be found at Clause 5.1 of the new Yellow Book.
This allows the Contractor within a specified period after Notice
of Commencement, to notify the Engineer of any error, fault or
defect in the Employer's Requirements. The Engineer then decides
whether to issue a variation. The Contractor is entitled to
extension of time and adjustment of the Contract Price, unless the
error was one which an experienced contractor would have
discovered before submitting his Tender, had he used reasonable
skill and care |
|
International Federation of Consulting Engineers FIDIC Bookshop- Box 311 - CH-1215 Geneva 15 - Switzerland Tl +41-22-799 49 00 - Fx +41-22-799 49 01 - fidic.pub@fidic.org - FIDIC Bookshop |